Client

Renewal SA

Project Length

8 Weeks

Project overview:

The redevelopment of the Bowden area, required a water main link from SA Water’s North Adelaide tank. An alternative method of construction was required in order to install the new main in tree lined street, through the North Adelaide golf course and under major roadways.

Description of work:

Engaged by Renewal SA to build the 1.3km 450 PE water main

  • SADB installed the pipeline via HDD and NDE
  • Works completed included multiple live tap into existing live trunk mains, valve and fire plug installations
  • Other works completed included concrete in situ thrust block, commissioning and testing of main