Client
DPTI
Project Length
4 Months
Project overview :
Delivered early works for service relocations of power, communications, gas and water infrastructure for the Darlington upgrade project.
Description of work:
- Project completed at night, under extensive traffic management
- All works completed to ensure 24 hours access for emergency vehicles to and from the Flinders Medical Centre
- 1.4km of CST installed via HDD and trenching
- Major road crossings completed under live traffic conditions
- Termination of all conduits and services to new manholes and connection to existing infrastructure