Client
City of Salisbury
Project Length
6 weeks
Project overview :
Design and construction of pedestrian underpass under Port Wakefield Rd. Dredging and re shaping of open drain.
Description of work:
- Undertook creek rejuvenation removing in excess of 400m³ of creek silt to allow high flow drainage
- Constructed 200 lm of concrete pavement to designed specification for sea water
- Constructed 20 lm of flood wall, doweling into existing bridge piers and constructed pavement, including water proofing membrane
- Dredging and removal of silt from existing open drain