Client
City of Salisbury
Project Length
2 Months
Project overview:
SADB undertook the supply and install 350 metres x 2100mm diametre concrete stormwater pipe. The system was linked to an existing catchment area and installed 5.5m deep, with final diversion into the Bridgestone Park Wetlands.
Description of work:
- All civil works for the supply installation of 2100mm diameter stormwater pipe- installed in roadway
- Supply and installation of precast head walls and precast junction pits
- Installation of gabion structure
- Extensive traffic control
- Relocation of existing underground services – water mains, sewer and stormwater
- Final commissioning and development
- Reconstruction of 400 metres of roadway