Client

City of Marion

Project Length

8 Weeks

Project overview:

SADB engaged by The City of Marion to complete a stormwater upgrade and installation of gross pollutant trap. Work completed in an environmentally sensitive zone along the beach foreshore.

Description of work:

Works Completed in 3 stages

  1. Installation of 450mm stormwater pipe, junction boxes and a small gross pollutant trap. System installed alongside operating Beach side café and customer car park.
  2. Link into existing stormwater system and installation new junction boxes. Installation of 6000mm x 5000mm x 4500mm large gross pollutant trap on beach foreshore. Extensive shoring and dewater required for the installation.
  3. Removal and disposal of existing damaged gross pollutant trap. Replaced with 1200mm diameter stormwater pipe link to the new gross pollutant trap.