Client

Coopers Brewery

Project Length

4 Months

Project overview:

Construct and install 4000m of 150 diametre steel transition gas main for the supply to Coopers Brewery development at Regency Park.

Description of work:

Gas main installed via HDD and trenching. HDD crossing under open drains, major roadways and large stormwater infrastructure. Additional works completed, included live connections to existing gas main, supply termination at Coopers site and the installation of 3 x concrete manholes.