Client
Public Transport Projects Alliance (PTPA)
Duration
5 Months
Project Objective:
Removal of the Ovingham Level Crossing and relocation of multiple SA Water assets to allow for the construction of a new bridge on Torrens Road
Description of Work:
SADB has been engaged by McConnell Dowel to relocate multiple sections of water and sewer main lines to make way for construction of a new bridge. SADB are installing the pipeline via HDD (Horizontal Directional Drilling), conventional trenching and NDE (Non-Destructive Excavation).
- Multiple cut ins to existing trunk mains
- Valve and fire plug installation
- Concrete thrust block to secure installations
- Commissioning and hydrostatic testing