Description of Work:
- Stage 1:
- 120 metres x 150mm PVC SN8 via trenching
- 5km x 125mm HDPE PN10 via HDD
- 11 x flushing points
- 2m x 4.1 deep pump sump
- 5 maintenance holes
- 90 x property connections
- CCTV & pressure testing
- Stage 2:
- Supply and Install 550 metres of 125mm PN16 via trenching
- 5 x flushing points
- 23 x property connections
- CCTV testing
- Test and pressure flush pipe
- Stage 2 Additional Scopes – Railway Tce South
- 450 metres of 125mm HDPE PN16 via HDD
- 39 x property connections
- 9 x flushing points
- CCTV & Pressure testing
- Stage 3:
- 600 metres of PVC PN6
- 29 x property connections
- 6 x flushing points
- 2 x maintenance holes
- CCTV & pressure testing
- Stage 4:
- 320 metres x 100mm PVC SN6 via trenching
- 100 metres x 125mm PN16 via HDD
- 3 x flushing points
- 2 x maintenance holes
- 31 x property connections
- CCTV & pressure testing