Description of Work:

  • Stage 1:
    • 120 metres x 150mm PVC SN8 via trenching
    • 5km x 125mm HDPE PN10 via HDD
    • 11 x flushing points
    • 2m x 4.1 deep pump sump
    • 5 maintenance holes
    • 90 x property connections
    • CCTV & pressure testing
  • Stage 2:
    • Supply and Install 550 metres of 125mm PN16 via trenching
    • 5 x flushing points
    • 23 x property connections
    • CCTV testing
    • Test and pressure flush pipe
  • Stage 2 Additional Scopes – Railway Tce South
    • 450 metres of 125mm HDPE PN16 via HDD
    • 39 x property connections
    • 9 x flushing points
    • CCTV & Pressure testing
  • Stage 3:
    • 600 metres of PVC PN6
    • 29 x property connections
    • 6 x flushing points
    • 2 x maintenance holes
    • CCTV & pressure testing
  • Stage 4:
    • 320 metres x 100mm PVC SN6 via trenching
    • 100 metres x 125mm PN16 via HDD
    • 3 x flushing points
    • 2 x maintenance holes
    • 31 x property connections
    • CCTV & pressure testing