Client

SAPN

Project Length

6 Weeks

Project overview:

QEH 33kV power upgrade. Installation of power circuit conduits and pole footing

Description of work:

  • Construction of 11 pole footings ranging from 3 metres to 5 metres deep and 900mm to 2500mm diametre.
  • Installation via HDD of 6 x 125mm electrical and 1 x 110 communications conduits