Client
DPTI
Project Length
2 Months
Project overview:
SADB engaged by DPTI, for the design and construction of early works for service relocation of SAPN infrastructure.
Description of work:
- Working under live rail conditions, SADB undertook 6 crossings at major intersections of road and rail
- High voltage and low voltage cables were installed
- HDD drills ranged from 4 x 125mm conduits to 10 x 125mm conduits
- Drill distance varied from 30 metres to 120 metres
- All conduit termination and precast pit installation was completed