Client

T2T

Project Length

2 Weeks

Project overview:

Installation of temporary gas main, decommissioning & removal of existing transmission gas main. Followed by the installation of a permanent 150mm transmission gas main. All works completed for the T2T Alliance on Port Rd.

Description of work:

  • The temporary 150mm transmission gas main was installed by HDD under live traffic conditions
  • The permanent 150mm steel gas main was installed at depths via NDE and gas main mechanical excavation