Client:

City of Tea Tree Gully

Duration:

18 Months

Description of Work:

The City of Tea Tree Gully reviews and assesses critical sections of the Community Wastewater Management System (CWMS) pipeline. Pipes that are subject to near-future failure due to poor condition or require upgrading to a larger pipe size due to increase peak flows from infill development are being replaced.

Further Project Details:

  • Works involved an extensive amount of directional drilling, trenching activities installing 450mm PE pipe, manhole/maintenance shaft construction, and property connections.
  • Total amount of direction drilling and trenching was 630 meters, 6 manholes, 2 maintenance shafts, and 14 property connections installed.
  • Social benefits to the project via Drilling included reduced disruption to the direct residents and the local neighborhood.