The Hampden Road pipeline and pump station is an integral part of the District Council of Mt Barker’s wastewater network and is an integral part of its future-proofing strategy.

  • Install:
    • 100 metres of 800mm carrier pipe via HDD
    • 120 metres of 560mm carrier pipe via HDD
    • 60 metres of 280mm carrier pipe via HDD
    • Tunnel bore and install SN64,000 GRP Jacking Pipe (OD1029)
    • 80 metres of 280mm carrier pipe via HDD
    • 140 metres of 800mm HDPE via micro tunnel